Third Party Maintenance in Zurich (ZRH2) Data Center January 23, 2020

Thursday, 23 January 4 hours
Complete
Complete

The scheduled maintenance has been completed.

Underway

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Scheduled

Third-Party carrier maintenance is currently underway in our Zurich (ZRH2) data center that started on January 23, 2020, at 01:00 UTC, and is expected to last up to 4 hours.

Impact There may be brief service disruption during the maintenance window.

Required Action IPSec connected customers will experience a brief degradation of service as the connections are switched over to the new network configuration.

Schedule

  • Start Date: January 23, 2020 at 01:00 UTC
  • End Date: January 23, 2020 at 05:00 UTC

  • Began at: