Network Maintenance in Mumbai Data Center April 5, 2019

Friday, 5 April 1 hour
Complete
Complete

The scheduled maintenance has been completed.

Underway

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Update

Please note: The maintenance time has been changed, the new maintenance window is:

Updated Schedule

  • Start Date: April 05, 2019 at 13:00 UTC
  • End Date: April 05, 2019 at 14:00 UTC

  • Scheduled

    Network maintenance will occur in our Mumbai Data Center on April 05, 2019 starting at 19:00 UTC and is expected to last up to 1 hour.

    Impact There will be a brief service interruption during the maintenance window.

    Required Action IPSec connected customers are requested to bring up their secondary tunnel (if configured) prior to the maintenance.

    Original Schedule

  • Start Date: April 05, 2019 at 19:00 UTC
  • End Date: April 05, 2019 at 20:00 UTC